There are some numbers (could be right or wrong)
* Remove from storage (2wks) based on previous
* Return to Everett to complete B & C testing (2 wks)
* Handover to QF and ferry ( 1 wk)
* Pre-service checks and service entry (1 wk)
That's if :
* Return to Everett where they were built
* No issues of waking them up from storage
* Boeing can slot them in at anytime (Remember QF recently place a large Airbus order)
* There is not rework due testing (no waiting for replacement parts)
* ....
Looking at the best case, 6 wks before service entry.
|