Hearing in regards to runway works.New runway final asphalt layer will be finished around 10 Oct in 1 month's time and final taxiway completions around Mid Dec this year.
Markings and lighting will then be commenced and from late Jan for the next 4 months links to the tower systems and runway calibrations will occur with a June-July 2020 opening.
The new runway will handle all Northern and Western movements such as GLT,ROK,TSV,CNS,ISA,Middle East,PNG,All Asia,Japan and China etc for both arrivals and departures .
Current runway will handle US,Pacific,NZ,SYD,MEL,ADL,CBR,PER etc for both arrivals and departures.
New runway will be closed from 11pm-6am each night .
On my flickr page there is a pic of new fire station being built.