Concreting of all the new taxiways was completed on 28Nov19.So both the runway construction and taxiway construction are now complete.

Grooving of the runway as well as lighting and markings will start soon.

Refurbishment of the Northern and central areas of the Domestic Terminal are now half way complete .Quite a few new stores are now open as well as refurbished current stores.A new food court opened in the last few days as well.